Mamrad ko kerman lime and dolomite plant
Project of assembly and installation and commissioning of lime and dolomite plant of mamrad ko kerman.
Project of assembly and installation and commissioning of lime and dolomite plant of mamrad ko kerman.
Project sections include:
Assembly and installation of furnaces weighing 1100 tons
Assembly and installation of material transmission lines system weighing 450 tons.
Assembly and installation of metal structure weighing 450 tons.
Assembly and installation of product tanks and storage of raw materials weighing 500 tons.
Assembly and installation blower weighing 250 tons performing of operation ducting in the amount of 50000 inch diameter
Start date: 1395/12/01
End date: 1398/06/15