PELLETIZING OF BOTIA
Installation project of material handling, electro filters , annular cooler ,Ball mill , flux system , wind system ducts , compressors and cooling tower of Boutia pelletizing
Installation project of material handling, electro filters , annular cooler ,Ball mill , flux system , wind system ducts , compressors and cooling tower of Boutia pelletizing
Installation of 55 conveyor Length : 5.5 km Weight : 2500 tons
Erection of transwer towers Weight : 700 tons
Installation of material handling equipment Weight : 500 tons
Assembly and installation of 3 electro filters Weight : 1500 tons
Assembly and installation of wind system duct Weight : 1100 tons
Assembly and installation of annular cooler unit Weight : 700 tons
Installation of Ball mill unit Weight : 300 tons
Installation of Flux system unit Weight : 100 tons
Installation of Compressors Weight : 50 tons
Installation of Tanks Weight : 100 tons
Assembly and installation of cooling tower unit